When I generate RRP I do not have any values in my work centres but I cannot find my setup error.
work centers are setup with rates, capacity and shift, hours and efficiency information
I have run the resource units refresh and using the enter/change resource units option I have inquired on my work centres. the capacity for my shifts by day has been populated and calculated correctly.
I have item forecasts.
I have generated the resource profile for my test items. labor run hours are correct. time basis is zero, which is also correct.
I then generated RRP. 0 planning weeks, 12 planning months with 2 past due periods. I didn't enter any percentages in the bucket info. with the correct forecast type.
My result ... work centre load is blank.
Does anyone have any suggestions for me. Thanks for your assistance.
work centers are setup with rates, capacity and shift, hours and efficiency information
I have run the resource units refresh and using the enter/change resource units option I have inquired on my work centres. the capacity for my shifts by day has been populated and calculated correctly.
I have item forecasts.
I have generated the resource profile for my test items. labor run hours are correct. time basis is zero, which is also correct.
I then generated RRP. 0 planning weeks, 12 planning months with 2 past due periods. I didn't enter any percentages in the bucket info. with the correct forecast type.
My result ... work centre load is blank.
Does anyone have any suggestions for me. Thanks for your assistance.