Anyone have a tool to estimate the number of CNC folks needed based on implementation factors like number of users, sites, uptime... etc?

Thanks!
Tom
AS400 - XE Upd. 6 - SP20 - HTML - Citrix
 
Hi Tom

Yes - I can help you with this if you wish - Please email me directly for a Microsoft Project Plan (98 format) - this works only for my customers and I'd rather not distribute this to other JDE or Business Partners that might quote differently for their projects. (Customers please feel free to email me for a copy).

The following is a high-level set of CNC timescales that I use to quote for a customers implementation.

Obviously, there are tasks beyond this list that are affected by items outside of the standard project scope.

Pre-Installation Technology IPS/PSW - 2 days onsite, 3 days documentation

Initial CNC Training (Internal Staff) - 10 days

Initial Installation (Non-AS400 Coexistence) - 10 days
Initial Installation (AS400 Coexistence) - 15 days
CNC Configuration and Setup - 5 days
Citrix implementation tasks - 3 days
QA Performance Testing - 2 days
QA Environment Build - 5 days
Automated Stress Test - 5 days
Pre-production tasks - 15 days
Additional tasks - 5 days

Total = 60 to 65 days

1 day = 8 hours

Additional scope would include but not be restricted to :

Standard Upgrade (15 days usually)
Major ASU (5 days)
ESU (1/2 day-1 day depending on size)
Full Package Build and Deployment (1 day)
Update Package and Deployment (depending on size)
Additional Application Server (5 days)
Initial JAS Server (10 days)
Additional JAS Server (5 days)
Technical Audit and Documentation (5-10 days)
Deployment Server rebuild (2-3 days)

Certain CNC Tasks that cannot be accurately identified (because of the differences between each case) include :
Retrofit (such as a Major Upgrade with modifications)
Replication (database to database server)
Database Migration (to another platform for example)
Interfaces (Batch, EDI, XPi, MQ Series, xmlCallObject etc etc)
 
Hey Jon,

Can you send me the Microsoft Project Plan.

Thanks
----- Original Message -----
From: "altquark" <[email protected]>
To: <[email protected]>
Sent: Tuesday, April 15, 2003 2:24 PM
Subject: Re: CNC Staffing Estimator?


directly for a Microsoft Project Plan (98 format) - this works only for my
customers and I'd rather not distribute this to other JDE or Business
Partners that might quote differently for their projects. (Customers please
feel free to email me for a copy).The following is a high-level set of CNC
timescales that I use to quote for a customers implementation. Obviously,
there are tasks beyond this list that are affected by items outside of the
standard project scope.Pre-Installation Technology IPS/PSW - 2 days onsite,
3 days documentationInitial CNC Training (Internal Staff) - 10 daysInitial
Installation (Non-AS400 Coexistence) - 10 daysInitial Installation (AS400
Coexistence) - 15 daysCNC Configuration and Setup - 5 daysCitrix
implementation tasks - 3 daysQA Performance Testing - 2 daysQA Environment
Build - 5 daysAutomated Stress Test - 5 daysPre-production tasks - 15
daysAdditional tasks !
include but not be restricted to :Standard Upgrade (15 days usually)Major
ASU (5 days)ESU (1/2 day-1 day depending on size)Full Package Build and
Deployment (1 day)Update Package and Deployment (depending on
size)Additional Application Server (5 days)Initial JAS Server (10
days)Additional JAS Server (5 days)Technical Audit and Documentation (5-10
days)Deployment Server rebuild (2-3 days)Certain CNC Tasks that cannot be
accurately identified (because of the differences between each case) include
:Retrofit (such as a Major Upgrade with modifications)Replication (database
to database server)Database Migration (to another platform for
example)Interfaces (Batch, EDI, XPi, MQ Series, xmlCallObject etc etc)
 
What do you mean Jon, by "Automated Stress Test?"
Dan
______________________________
Dan Doenges
Dir of Technical Services
Department 56, Inc.
6436 City West Parkway
Eden Prairie, MN 55344
Office: (952) 943-4467
Mobile: (952) 240-0967
Fax: (952) 826-1203





OW 7321, SP 12.5, coexistant, ES 400 V5R2, DS Win2000
 
Back
Top