Jim,
We have two AS/400's here at White-Rodgers. Production is on one
machine. On the Development/testing/Mirrored machine, we have several
environments. One is a setup environment, used for testing and turnover
promotions. We have a Production AS OF environment, that is production as
of 2200 the previous day. We also have a development environment. On a
daily basis, we back up Production from a mirrored copy on the second AS/400
to a save file. We then restore from the save file to the AS OF libraries.
We have a process (did not program it, so would have to look it up) to on
occasion refresh the other development environments from Production, but not
having the full F0911 file and other big files out there. But again we have
mirrored production to the second AS/400, which probably makes things easier
than if that is not the case.
John Dickey
JDE Financial Systems Administrator/Programmer/Analyst
White-Rodgers, Division of Emerson
St. Louis, MO
314-577-1466