Hi All - I am new to JDE Enterprise One. if we set up the routing for an item that has more than one step in the operation sequence (for this example Operation Sequence 10.0 and 20.0) My question is this:
Does the system calculate for both steps each time the part is created? Or can you set up the routing so that it will only charge for one or more steps (sequences) based on certain conditions?
I do not know how to set up conditional routing if it exists - is there any documentation regarding this?
Does the system calculate for both steps each time the part is created? Or can you set up the routing so that it will only charge for one or more steps (sequences) based on certain conditions?
I do not know how to set up conditional routing if it exists - is there any documentation regarding this?