    Hi All,

    I have the following MRP scenario I'm struggling with.

    Back Orders / Open Orders and Marketing forecast. Then I have a weekly capacity – is it possible for me to stop MRP from suggesting more per week than the capacity per week. ( I also have MOQ’s on the line runs during the week too).

    Any ideas will be appreciated – thank you!!

    (8.11 SP1)

  2. #2
    New Member
    Join Date
    Oct 2012
    Location
    Victoria Australia
    Posts
    11
    Hi Lally421

    Unfortunately MRP is not capacity constrained. Therefore it will suggest that you manufacture the qty needed to satisfy the demand irrespective of the capacity available.
    You can enter a maximum order qty that equals either your daily or week capacity. MPS/MRP will then create multiple orders when you exceed this daily or weekly capacity. For example: If you enter daily capacity and you receive more than five work order messages for the week you know you have exceeded your capacity ( similarly if you enter weekly capacity as max order qty and you receive more than one order for the week.) The planner can then make a decision on other means to fulfill the extra demand (overtime, extra shift or outsource if theses options are possible) or liaise with the sales staff to try to move the demand to another period or product!! Not a great solution but without going to the Advanced planning Modules there are not a lot of options.
    Marilyn Threlfall
    JDE Manufacturing / Distribution Consultant
    www.jdeasysoftware.com

  3. #3
    New Member
    Join Date
    Aug 2005
    Location
    Australia
    Posts
    10
    MRP is unconstrained planning, it will plan work orders to meet your customer and forecast demand. It does not look at your capacity.
    JDE Capacity Planning will highlight if a work centre is over / under capacity based on both firm and planned work orders.
    You then have to reschedule these planned orders or adjust capacity to meet the demand.
    How is your forecast loaded, is this weekly or monthly - if monthly then JDE MRP will plan to meet the full forecast demand by the request date (for the full months demand)
    You may be better loading a weekly forecast and setting the Planning Fence Rule so that Customer orders consume the forecast.

    Regards - Vic Clarke

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
The legal restrictions and terms of use applicable to this site are available here.
Use of this site signifies your agreement to the terms of use.
JDELIST is NOT affiliated with JD Edwards® & Company, Oracle or Peoplesoft. Contents of this site are neither endorsed nor approved by JD Edwards® & Company and, or Oracle.