Work In Process

MIMAMZ

Member
Dear all,

How we get work in process (WIP) report form JDE ?
Report it's mean I would like to get WIP in Paper for all Item.

regards,
IMAM
 
A bit unclear as to what you are actually asking.
Are you after a report of WORK ORDER WIP value ??
If Yes then the bad news is there is no standard available report (Pre8.9
anyhow).

You will probably have to have a report written.

If you use the WO number in the subledger field and have only a few WIP G/L
accounts then you could consider writing a WIP report based on G/L F0911.

Probably a better bet is to write report based on F3102 (Work order cost
file.) Here report can be based around Actual values less completed scrap
values. You can use data selection to limit to work orders at a certain
status, for a certain branch plant etc...
 
Your question is too vague... What do you mean? WIP is all things to all men. The simple answer is to learn ERW and write the report (or Crystal, et al).... Do you want Open Work Orders or something from the G/L to indicate its value? Do you need a dispatch report showing where all the WO's are (try R31435)?

A WIP report is generated when R31802 is run which shows all the Journals for that generation. Go to menu G3116 and try Reports R31812A & R31812B... Are they what you are after? Try menu G3123 for all the Mfg Accounting Reports. Try menu G3121 for the R31400 WO Summary and others....

If none of these are what you are after write something new yourself. I would be happy to give you and indicator as to where all the data is if you let us all know what you need to see on the report.

Good luck.
 
Back