URGENT : Bug in MRP (R3482) Partial consumptions on components not taken in account in subsequen MRP

mateo31

Active Member
URGENT : Bug in MRP (R3482) Partial consumptions on components not taken in account in subsequen MRP

Dear all,
Since our Xe -> 810 migration, all our subsequent MRP doesn't take care about partial consumptions on components Technically, we would wish get a work order requirement = Quantity required - quantity issued (WMUORG - WMTRQT instead of WMUORG in the part list table F3111 for the components
)
As a result, our time series are wrong and our purchase order message are surestimated. We've applied a ESU but the problem still exists.

Could you help me ? (Quantity types 34/QT or supply/demand inclusion rules ???)
 

Attachments

  • 112882-Abnormal quantity in MRP.doc
    286 KB · Views: 174
Re: URGENT : Bug in MRP (R3482) Partial consumptions on components not taken in account in subsequen MRP

Just some questions, are you running in gross regen or net change? Does your version of supply/demand inclusion rule (used in R3482) have your WO status for partial completion switched on? Other than that it is difficult to say what it could be without knowing details of yur configuration.
 
Re: URGENT : Bug in MRP (R3482) Partial consumptions on components not taken in account in subsequen MRP

Thanks
We use a gross generation and there is no specific WO status when there is partial completion. The WO cycle is very simple : 10-40-55-90. Anyway, the supply/demand inclusion rule selects almost all the WO status (see attached file).

Are you in the same version ?
 