this has been discussed before but I am still unable to do what I need to do.
We are live on financials and are preparing other modules now. We need to selectively copy tasks from PY to PD. We do not want to copy the entire control tables. I have read document ott-01-0066 and still can´t figure it out.
Is there any option that copies a whole task tree via P9864A?
Can I at least copy an entire folder with it´s tasks (what we used to call a menu with it´s menu options) ? We have quite a few folders (menus) to copy.
Thanks for any help!
We are on E8.9, SP2, AS400, WTS
Thanks, Gerd
this has been discussed before but I am still unable to do what I need to do.
We are live on financials and are preparing other modules now. We need to selectively copy tasks from PY to PD. We do not want to copy the entire control tables. I have read document ott-01-0066 and still can´t figure it out.
Is there any option that copies a whole task tree via P9864A?
Can I at least copy an entire folder with it´s tasks (what we used to call a menu with it´s menu options) ? We have quite a few folders (menus) to copy.
Thanks for any help!
We are on E8.9, SP2, AS400, WTS