Our issue is that when we are freezing costs and choose to Update Costs (PO 1) and also Update Work Centre Rates (PO3), all the work centre rates are frozen regardless.
Does any one have a solution to being able to control what work centre rates are frozen? We use are our data selection the item branch and 2nd item number and would like for the program to pick these values and pass them through to the work centre update business function.