Chris48
Member
We associate master routings to phantom items as many service items are sold as phantoms and we want to account for the labor cost. The standard cost of the phantom item includes the B and C labor cost elements as long as the master routing item is on the BOM of the phantom. Unfortunately, the planned and completed WO cost does not include the labor cost associated with the phantoms within a multi-level BOM structure. The variances this produces must be reclassified to cost of sales. Does anyone have any idea how to correct the issue so that work order planned and actual cost includes the master routing labor of the phantoms?