P48013 Production Work Order Start Dates don't match on the Routing

AlmaS

Active Member
P48013 Production Work Order Start Dates don\'t match on the Routing

Hi,

Does anyone know if you can change the start date on a production work order and have it match the parts list and routing start date? The backscheduling using leadtime, may not always be accurate for the scheduler. I find the parts list will update, but not the routing.

Thanks,
Alma
B733.2 upgrading to 8.10
issue in both
 
Back
Top