Hi,
Does anyone know if you can change the start date on a production work order and have it match the parts list and routing start date? The backscheduling using leadtime, may not always be accurate for the scheduler. I find the parts list will update, but not the routing.
Thanks,
Alma
B733.2 upgrading to 8.10
issue in both
Hi,
Does anyone know if you can change the start date on a production work order and have it match the parts list and routing start date? The backscheduling using leadtime, may not always be accurate for the scheduler. I find the parts list will update, but not the routing.
Thanks,
Alma
B733.2 upgrading to 8.10