Is anyone using Rapid Planning with JDE 9.1 (with or without JDE MRP/MPS)?
We are comparing Advanced Supply Chain Planning, Rapid Planning and MRP. It appears to us that MRP would work fine for our longer term materials plans (we have some long lead time items - 6 months plus) but we need the simulation capability of Rapid Planning (or similar) to look at the effects of short term BOM changes, capacity constraints etc.
Any help would be much appreciated.
We are comparing Advanced Supply Chain Planning, Rapid Planning and MRP. It appears to us that MRP would work fine for our longer term materials plans (we have some long lead time items - 6 months plus) but we need the simulation capability of Rapid Planning (or similar) to look at the effects of short term BOM changes, capacity constraints etc.