rmerrell
Member
I am testing MRP in release E900 and I am seeing the "Date Generation Failed" error in the PDF when I run the R3483 on the server.
I have shop-floor calendars through 2021 (10 years) in the branch/plant I include in data selection as well as branch/plant ALL. I also have monthly F3405 records loaded through 2021 since the item I am testing uses forecast consumption logic (hence F4102.IBMPSP=H and IBMTF1=999). There are no months missing in either the F0007 or F3405.
If I run the test LOCALLY, R3483 COMPLETES SUCCESSFULLY.
Does anyone know of any other data elements/set-up requirements that could cause this error?
Thanks!
RMerrell
Business Systems Analyst
DeRoyal Industries, Inc.
I have shop-floor calendars through 2021 (10 years) in the branch/plant I include in data selection as well as branch/plant ALL. I also have monthly F3405 records loaded through 2021 since the item I am testing uses forecast consumption logic (hence F4102.IBMPSP=H and IBMTF1=999). There are no months missing in either the F0007 or F3405.
If I run the test LOCALLY, R3483 COMPLETES SUCCESSFULLY.
Does anyone know of any other data elements/set-up requirements that could cause this error?
Thanks!
RMerrell
Business Systems Analyst
DeRoyal Industries, Inc.