We have one JDE EnterpriseOne 8.10 instance on 8.97.1 with two AS400 Enterprise/DB servers on V5R3. One server hosts DV/PY and the other hosts PD, system, and security. Oracle is recommending that we upgrade both servers at the same time. I would like to upgrade the DV/PY server first and then a week or two later, upgrade the PD server. I was also planning on leaving the client access at V5R3 until after bother servers are upgraded.
Has anyone had any experience with doing this separately? Any gotcha's we should look out for? I am looking at the latest APAR list.