Hello List…I’m hoping a few kind hearted souls will be willing to answer some very general upgrade questions as I have never performed one…or seen one for that matter.
We are a relatively small OneWorld Xe installation…with myself being the only CNC tech and DBA. I am trying to estimate the time and cost of both an ERP 8.0 and an ERP 8.9 upgrade.
We currently only have two environments (DV7333, and PD7333), although I can rebuild CRP if need be. Also, we have very few custom mods, so custom upfits could probably happen in one day.
Some questions I am trying get answered (for both upgrade options) are:
1) About how long will each type of upgrade take per environment? For instance, can I upgrade DV7333 one weekend, and then prod over another weekend? Or can it exceed 48 hours?
2) Based on the list’s experiences, are there portions of the upgrade that can easily be performed by inexperienced CNC techs (who are rather good at following directions)? Which portions?
a. Also, are there portions of the upgrade that you would suggest having consultants available for?
b. For those portions of the upgrade, is remote consultancy acceptable – or is on-site consultancy required?
Thanks in advance for any and all assistance.
We are a relatively small OneWorld Xe installation…with myself being the only CNC tech and DBA. I am trying to estimate the time and cost of both an ERP 8.0 and an ERP 8.9 upgrade.
We currently only have two environments (DV7333, and PD7333), although I can rebuild CRP if need be. Also, we have very few custom mods, so custom upfits could probably happen in one day.
Some questions I am trying get answered (for both upgrade options) are:
1) About how long will each type of upgrade take per environment? For instance, can I upgrade DV7333 one weekend, and then prod over another weekend? Or can it exceed 48 hours?
2) Based on the list’s experiences, are there portions of the upgrade that can easily be performed by inexperienced CNC techs (who are rather good at following directions)? Which portions?
a. Also, are there portions of the upgrade that you would suggest having consultants available for?
b. For those portions of the upgrade, is remote consultancy acceptable – or is on-site consultancy required?
Thanks in advance for any and all assistance.