Our company has just started investigating the use of PO Generator. We have formed an alliance with our sub-contractors and are looking to provide them with the ability to manage the inventory levels at their locations.
During our testing we found that PO Generator does not create a record in the hold file (F4209). One of our programmers who looked into the PO Generator program found that PO Generator does not follow the purchase order approval process, but instead uses budget approvals.
Has anyone worked with PO Generator and/or budget approvals? We're looking for any option or work-around.
Mary A. Massaro
During our testing we found that PO Generator does not create a record in the hold file (F4209). One of our programmers who looked into the PO Generator program found that PO Generator does not follow the purchase order approval process, but instead uses budget approvals.
Has anyone worked with PO Generator and/or budget approvals? We're looking for any option or work-around.
Mary A. Massaro