Is there any MRP processing option to change the logic behind when JDE plans the next PO based on other firm PO's?
For example, say I have part #999 and I've placed PO's at lead time plus 4 months. Currently, if there is increased demand in the schedule/forecast outside of the part's LT, JDE will suggest you first expedite the firm PO's and then place new PO's after that.
How do I get JDE to suggest a new PO to satisfy any demand gap outside the part's LT instead of trying to expedite x amount of POs first?
Thanks,
Joe
For example, say I have part #999 and I've placed PO's at lead time plus 4 months. Currently, if there is increased demand in the schedule/forecast outside of the part's LT, JDE will suggest you first expedite the firm PO's and then place new PO's after that.
How do I get JDE to suggest a new PO to satisfy any demand gap outside the part's LT instead of trying to expedite x amount of POs first?