DEddy
Active Member
We are upgrading from our current IBM i Power 7 to a new IBM i Power 9.
This will be a hardware only upgrade. Our current OS/400 is compatible with the new hardware. Our plan is to use the same server name and IP address on the new box as the old one.
A basic outline of our plan is as follows:
• Change QSTRUP to not bring up JDE
• GO SAVE: Option 21 backup of Power 7
• Shut down current Power 7
• Power up new Power 9 – (use same IP address and name as old Power 7)
• Restore from backup
• After system comes up, change QSTRUP to bring up JDE
• Test
Are there any gotcha's that might cause JDE to have problems by just doing a backup / restore to new box?
9/18/19 Followup to above upgrade. This plan worked. We are running on new Power 9 system.
This will be a hardware only upgrade. Our current OS/400 is compatible with the new hardware. Our plan is to use the same server name and IP address on the new box as the old one.
A basic outline of our plan is as follows:
• Change QSTRUP to not bring up JDE
• GO SAVE: Option 21 backup of Power 7
• Shut down current Power 7
• Power up new Power 9 – (use same IP address and name as old Power 7)
• Restore from backup
• After system comes up, change QSTRUP to bring up JDE
• Test
Are there any gotcha's that might cause JDE to have problems by just doing a backup / restore to new box?
9/18/19 Followup to above upgrade. This plan worked. We are running on new Power 9 system.