GOOD DAY!
I AM HAVING TO MODIFY APPLICATION P4210 SALES ORDER ENTRY. I AM ADDING 4
ELEMENTS INTO THE GRID. THIS I DON'T HAVE A PROBLEM WITH. MY PROBLEM IS I
HAVE 39 VERSIONS IN PRODUCTION WITH DIFFERENT PROCESSING OPTIONS. MY
QUESTION IS DO I HAVE TO DO ANYTHING WITH THESE VERSIONS AND THERE
PROCESSING OPTIONS FROM PRODUCTION BEFORE I PROMOTE MY PROJECT IN OMW AND DO
A PACKAGE BUILD, SO I DON'T LOOSE MY PROCESSING OPTIONS.
I NOTICED THAT WHEN I DID A PACKAGE BUILD TO PROMOTE MY APPLICATION TO MY
TEST AREA IT AUTOMATICALLY DID A BUILD ON THE VERSIONS EVEN THOUGH I DID NOT
HAVE THEM IN MY PROJECT ON OMW.
THANK YOU! IN ADVANCE FOR YOUR HELP!
Bob Bushley
Haskel International
Burbank, Ca. U.S.A.
XE(B7333)ver SP15.1
AS400 ver V4R5 DB2
Windows 2000 SR2
I AM HAVING TO MODIFY APPLICATION P4210 SALES ORDER ENTRY. I AM ADDING 4
ELEMENTS INTO THE GRID. THIS I DON'T HAVE A PROBLEM WITH. MY PROBLEM IS I
HAVE 39 VERSIONS IN PRODUCTION WITH DIFFERENT PROCESSING OPTIONS. MY
QUESTION IS DO I HAVE TO DO ANYTHING WITH THESE VERSIONS AND THERE
PROCESSING OPTIONS FROM PRODUCTION BEFORE I PROMOTE MY PROJECT IN OMW AND DO
A PACKAGE BUILD, SO I DON'T LOOSE MY PROCESSING OPTIONS.
I NOTICED THAT WHEN I DID A PACKAGE BUILD TO PROMOTE MY APPLICATION TO MY
TEST AREA IT AUTOMATICALLY DID A BUILD ON THE VERSIONS EVEN THOUGH I DID NOT
HAVE THEM IN MY PROJECT ON OMW.
THANK YOU! IN ADVANCE FOR YOUR HELP!
Bob Bushley
Haskel International
Burbank, Ca. U.S.A.
XE(B7333)ver SP15.1
AS400 ver V4R5 DB2
Windows 2000 SR2