Receipt routing and overshipment

dikdik

Member
The customer i am working for wants to track the purchase receivements from the moment the goods leave the warehouse of the supplier.
So, we are using receipt routing.
When the goods arrive at our warehouse the exact numbr of items is known. In some cases there is a overshipment.

Does anybody have any suggestions ho to handle overshipments while the purchase receipt is in receipt routing.

we are working with JDE 8.0 service pack 20.

Thanks in advance.
Dirk Dijkstra
CGE&Y, The Netherlands
 
Dirk,

What is your desired business process to handle this overship situation...

a. Pay the Supplier for the extra goods (what would be the sort of
tolerance that you would allow on this??)
b. Send the goods back to the Supplier (maybe the Supplier will give them
to you at a discounted price to save them the freight cost of returning
them)
c. Don't tell anyone and take the extras ;-] (Stock Adjustment)

As you are aware the Movement & Disposition program does not cater for
overships, so if your business process is (a) you would need to create a
P.O line to receive these goods. You could probably debate that since P.O
Receipts can allow overshipment then Movement & Disposition probably should
as well, however as it doesn't (and the mods required to manage the
quantity differences in the Routing file and Values in the G/L would be
heavy) it is probably worth your while to push (b) or (c) as the approach
to take.

Regards,

Potsy



**********************************************************************
This email and any files transmitted with it are confidential and
intended solely for the use of the individual or entity to whom they
are addressed. If you have received this email in error please notify
the system manager ( [email protected] )

Important Notice: Berri Limited scans all incoming and outgoing
emails for possible inappropriate content. Procedures to rectify
problems with the email system may result in others reviewing
the content of any incoming or outgoing email.

The Berri Limited Email system is for Business use only.

**********************************************************************



Craig Potte
 
Craig,

Thanks very much for your quick answer.
Your described business process under a) is the right one. We do have to pay for the goods.

Creating a new P.O. line is exactly what we thought. I was hoping for a less time-taking solution. But unfortunately.....

Thanks very much!!

Dirk
 
If you want to prevent over recieving, set your tolerances to prevent over recieving (ie. no more than the purchase order quantity or percentage).
 
Back