P.O. Start Date

Kumars

Active Member
Dear Group,

My routing instruction for a manufactured item has got
3 operation steps in three different work centers.
Each operation is taking 3 days time to complete.
ie. 9 days totally to complete the 3 routing steps.
I have got one purchased item attached with the 3rd
operation in the BOM. When I run the MPS/MRP, I expect
the request date of the P.O. should be equal to the
start date of the 3rd operation. i.e. on the 7th day
after the work order start date. But, I am getting P.O.
request date on the start date of the work order. Kindly
suggest what should I do, so that, I get the purchased
items right in the time when I need it.

Thanks,
S.Kumar
 
Try to use the "Leadtime Offset" field in BOM to get the materials either earlier or later than the WO start date.
Regards,
John Hsiao, Xe ERP8, SP19
 