Set up a different version of inventory issues program for that particular situation (partials) to be called by a version of completions used for partials. I have done this in and the only problem is making sure people use the right program. you could tie this to a menu selection such as partial completions...
Good luck
Willaim [email protected] wrote:
(MTST)to a different status for partial issues than for full issues. I know
that when an issue is done, the material status is updated to whatever
status is specified in processing option 3 on P31113 - but it does not
differentiate between partial or full issues.