Hi...
Does the F4311 End Document Master business function executed asyncronously. I have added some codes just after the MBR to update the table F4311 with some values.
However, it seems that my codes have been executed and then the purchase order is committed to the table.
But if I put the debugger on...then everything is fine, the purchase order is committed first and then my codes are executed...
Am I correct? If Yes...Is there a solution for that?
That's very Strange!!
Thanks
Does the F4311 End Document Master business function executed asyncronously. I have added some codes just after the MBR to update the table F4311 with some values.
However, it seems that my codes have been executed and then the purchase order is committed to the table.
But if I put the debugger on...then everything is fine, the purchase order is committed first and then my codes are executed...
Am I correct? If Yes...Is there a solution for that?
That's very Strange!!
Thanks