johndanter
Legendary Poster
I've been asked to look at a way of changing 3 fields on a PO and also cancelling a line. Quantity, Price and Promised Del Date
I've been told to change our existing Inbound 856 process UBEs.
EBI writes to F47031/32 and then wakes up a clone of R47031 which populates F4301Z1 / 11Z1 before calling a clone of R4311Z1I to write to F4311 / 11 proper
It's only 3 fields we need changing, that's overkill what they've suggested, right?
How would others go about it?
Write to F4311Z1 directly?
Ta
John
I've been told to change our existing Inbound 856 process UBEs.
EBI writes to F47031/32 and then wakes up a clone of R47031 which populates F4301Z1 / 11Z1 before calling a clone of R4311Z1I to write to F4311 / 11 proper
It's only 3 fields we need changing, that's overkill what they've suggested, right?
How would others go about it?
Write to F4311Z1 directly?
Ta
John