The P4211 uses the order activity rules starting values for the sales doc t ype and the item line type for each line. Processing options 3 and 4 can o verride these too.
If you are getting a next status between 900-998 it is because of something that the program determined about the line such as the following:
900 - item was backordered during sales order entry
902 - item was backordered during commitments
904 - item was backordered during shipping confirmation
912 - item added during commitment
914 - item added during shipping confirmation
920 - item added during order repricing
920 - item added during work order generation
980 - item cancelled during sales order entry
980 - item cancelled during commitments
984 - item cancelled during shipping confirmation
988 - item cancelled during update
Jim
From: lfolk627 [mailto:
[email protected]]
Sent: Friday, June 08, 2012 11:50 AM
To:
[email protected]
Subject: SO Next Status Code Update
I am looking for the program and/or copy source in JDE World that updates t he SO status code during execution of the SO entry(P4211) program. I know i t will pull the next status code based on order activity rules. The reason I am looking for the RPG code is because for specific items it is pulling i n the wrong next status even though the doc type and line type is the same as for the items that it pulls in the correct status. It must be checking s ome other parameter of the item, i.e branch, item planning family, etc...? So Thoughts? Knowledge of program and/or copy source name?
Lynn Sr. IT Application Specialist