nitingl
Member
Hi,
One of our client has a requirement to use Minimum Order Quantity while ordering(creating PO) from MRP message processing P3411.
As i understand,Minimum Order Quantity concept is provided by JDE only for items planned by Reorder Point ad not by MRP. Is it possible to define a MOQ (Minimum Order Quantity) and plan that item by MRP and finally when processing MRP message(P3411) Order MOQ as opposed to Order Quantity on message.
Thanks,
Nitin
One of our client has a requirement to use Minimum Order Quantity while ordering(creating PO) from MRP message processing P3411.
As i understand,Minimum Order Quantity concept is provided by JDE only for items planned by Reorder Point ad not by MRP. Is it possible to define a MOQ (Minimum Order Quantity) and plan that item by MRP and finally when processing MRP message(P3411) Order MOQ as opposed to Order Quantity on message.
Thanks,
Nitin