Consolidating Outside Operations for multiple WO\'s
I've seen some posts on outside operations from the past few years, but thought I'd see if there's any new functionality or ideas out there on the issue of consolidating outside operations for multiple WO's.
Our issue has come about because if we process WO's "normally", we end up with one outside processing PO (at least) per WO. Several of our suppliers include a "setup charge" on a per-PO basis. So even if we have 4 or 5 outside operations to send to the supplier at the same time, we will get hit with the "setup charge" on each of the PO's. We would really like to be able to consolidate these outside operations onto a single PO. Has anyone else run into this situation, and/or do you have any ideas on how this can be addressed?
I've seen some posts on outside operations from the past few years, but thought I'd see if there's any new functionality or ideas out there on the issue of consolidating outside operations for multiple WO's.
Our issue has come about because if we process WO's "normally", we end up with one outside processing PO (at least) per WO. Several of our suppliers include a "setup charge" on a per-PO basis. So even if we have 4 or 5 outside operations to send to the supplier at the same time, we will get hit with the "setup charge" on each of the PO's. We would really like to be able to consolidate these outside operations onto a single PO. Has anyone else run into this situation, and/or do you have any ideas on how this can be addressed?