Muhammad Mudasar Ansari
Member
Hi all,
I need some suggestion regarding setup of BOM.
We are a pharmaceutical company.
We have defined a process having batch quantity of 10,000 and its ingridients using application "Enter / chagne process - P3003".
For this process, there will be only one co product, no by product is defined.
10,000 unit of co product will be produced at the end of this process.
In Leadtime inquiry - P30200 application, system is multiplying batch quantity with ingridient quantity to calculate extended quantity, for example
Batch Quantity = 10,000
Ingridient Qty
RMI0004 10kg
Extended Quantity = 100,000
which is not required. We have defined 10kg of RMI0004 to produce 10,000 unit in batch.
Please advise what wrong I am doing.
Regards,
Mudasar
I need some suggestion regarding setup of BOM.
We are a pharmaceutical company.
We have defined a process having batch quantity of 10,000 and its ingridients using application "Enter / chagne process - P3003".
For this process, there will be only one co product, no by product is defined.
10,000 unit of co product will be produced at the end of this process.
In Leadtime inquiry - P30200 application, system is multiplying batch quantity with ingridient quantity to calculate extended quantity, for example
Batch Quantity = 10,000
Ingridient Qty
RMI0004 10kg
Extended Quantity = 100,000
which is not required. We have defined 10kg of RMI0004 to produce 10,000 unit in batch.
Please advise what wrong I am doing.
Regards,
Mudasar