JEVERETT
Member
I am looking into using the WO Mass update program (P48022) so planners can easily update multiple Work orders dates.
I have been following the Oracle documentation on how to set it up and it all makes sense but I would like to lock down further to which work orders the users can update. I would like to set that they can't update if the Work order(s) are past a specific status.
R48714 Mass update UBE is part of the setup, and I have created a version with data selection to not allow Work orders greater than a status, but the problem is there is no where in the P48022 or P48714 program that allows me to enter the version of R48714 to call?
Am I not going at this correctly? I've been told that I can control which work orders planners can update, but I can't find anywhere else to set this besides the R48714.
Any ideas or help would be appreciated!
I have been following the Oracle documentation on how to set it up and it all makes sense but I would like to lock down further to which work orders the users can update. I would like to set that they can't update if the Work order(s) are past a specific status.
R48714 Mass update UBE is part of the setup, and I have created a version with data selection to not allow Work orders greater than a status, but the problem is there is no where in the P48022 or P48714 program that allows me to enter the version of R48714 to call?
Am I not going at this correctly? I've been told that I can control which work orders planners can update, but I can't find anywhere else to set this besides the R48714.
Any ideas or help would be appreciated!