JHD
Member
Help please.
We are running OneWorld ERP8 SP5 on our as/400 server.
We want our master planner to drive production not straight demand and forcast. Is there a way to make master planning have control over what MRP does? Here is the example.
Sep 100 of part a ordered, Oct 500, Nov 100.
The system forces us to build 100 and aquire parts for 100 in Sep. but master planning wants to build 250 this month, 250 next and 200 the following. The system will not allow the 250 this month. MRP still forces 100 even if the forcast is upped to 250.
Hope that was clear as mud sorry i'm tring to relay what the master planner is telling me.
thank you
Joe
We are running OneWorld ERP8 SP5 on our as/400 server.
We want our master planner to drive production not straight demand and forcast. Is there a way to make master planning have control over what MRP does? Here is the example.
Sep 100 of part a ordered, Oct 500, Nov 100.
The system forces us to build 100 and aquire parts for 100 in Sep. but master planning wants to build 250 this month, 250 next and 200 the following. The system will not allow the 250 this month. MRP still forces 100 even if the forcast is upped to 250.
Hope that was clear as mud sorry i'm tring to relay what the master planner is telling me.
thank you
Joe