rb43td
Member
I've come across something I've not see before. When creating a plant transfer (ST), we are seeing the Scheduled Pick Date (PDDJ) adjust itself correctly on a finished good order but not on a raw material order. For example, we have a 2 day transit from one Branch/Plant to another. I create the ST for the finished good product and put 06/20/15 as the Request Date (DRQJ). After creation the Scheduled Pick Date shows 06/18/15. This is correct because of the 2 day transit. I then create another ST for the exact same Branch/Plants but this time I'm transferring a raw material item. I put the same 06/20/15 Request Date in but after creation the Scheduled Pick Date shows 06/20/15 instead of the 06/18/15.
Any thoughts on why the item type would be affecting the PDDJ calculation and where that setting can be reviewed?
Thanks!
**Just wanted to add that I noticed something new in testing. It actually doesn't appear to be only related to the item type, but to the actual item itself and a carrier being auto-assigned. This is still confusing me because I'm not changing anything on the ST creation except the item number. Some of the items do cause a carrier to be assigned at time of ST creation and that's allowing the Pick Date calculation while the other items result in no carrier being assigned and that is where I see the Pick Date being the same as the Request Date. Any ideas on why a carrier would be assigned for some items and not others?
Thanks!
Any thoughts on why the item type would be affecting the PDDJ calculation and where that setting can be reviewed?
Thanks!
**Just wanted to add that I noticed something new in testing. It actually doesn't appear to be only related to the item type, but to the actual item itself and a carrier being auto-assigned. This is still confusing me because I'm not changing anything on the ST creation except the item number. Some of the items do cause a carrier to be assigned at time of ST creation and that's allowing the Pick Date calculation while the other items result in no carrier being assigned and that is where I see the Pick Date being the same as the Request Date. Any ideas on why a carrier would be assigned for some items and not others?
Thanks!
Last edited: