E9.0 Can we change Unit of Measure after PO Receipt is done.

Macpal

Member
After PO receipts is done can we correct the Unit of Measure if we are getting error in AP voucher match.
 
You'd need to reverse the PO Receipt, make the UM change, re-receive the PO, and then try the voucher match again.
 