Thread: Outside operation with multi suppliers

  1. #1

    Outside operation with multi suppliers

    Hi,
    We have a business case that we have an item which is subtracted to two different suppliers. We use R31410 to create *OP purchase order for the manufacture cost of this item. But in routing, we can only setup a supplier for this item at one time. We have to change the supplier in routing from time to time if we need two suppliers. It's inconvenient. Is there any solution to make it easy?
    E1 8.12,Windows Server 2003,Oracle

  2. #2
    Quote Originally Posted by catthunder View Post
    Hi,
    We have a business case that we have an item which is subtracted to two different suppliers. We use R31410 to create *OP purchase order for the manufacture cost of this item. But in routing, we can only setup a supplier for this item at one time. We have to change the supplier in routing from time to time if we need two suppliers. It's inconvenient. Is there any solution to make it easy?
    Hi,

    we used M route that set in item route (p3003) for primary subcontractor. for secondary vendor , we set in A route.

    often the planner or buyer jumped to modify supplier on the the w/o route in advance, or modify the *OP supplier when release the order.

    R/L

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
The legal restrictions and terms of use applicable to this site are available here.
Use of this site signifies your agreement to the terms of use.
JDELIST is NOT affiliated with JD Edwards® & Company, Oracle or Peoplesoft. Contents of this site are neither endorsed nor approved by JD Edwards® & Company and, or Oracle.