HI There,
We are in the process of implementing the multi locations MPS/MRP and CRP in JDE 9.0.
We are struggling to make the MRP system works so that:
> MRP messages for work orders (Expedite, increase etc...) do not trigger changes in lower level (purchased items) requirements until they are being reviewed and firmed by the planners (at least of a defined time horizon)
> We do want to run net change and get messages but do not want to pass the requirements to procurement automatically; only when firmed
> However, we want the MRP messages to generate requirements in the longer term horizon outside of purchasing components lead time (4 months +)
Anyone has faced similar challenges and found a way to resolve it?!
Jonathan
We are in the process of implementing the multi locations MPS/MRP and CRP in JDE 9.0.
We are struggling to make the MRP system works so that:
> MRP messages for work orders (Expedite, increase etc...) do not trigger changes in lower level (purchased items) requirements until they are being reviewed and firmed by the planners (at least of a defined time horizon)
> We do want to run net change and get messages but do not want to pass the requirements to procurement automatically; only when firmed
> However, we want the MRP messages to generate requirements in the longer term horizon outside of purchasing components lead time (4 months +)
Anyone has faced similar challenges and found a way to resolve it?!
Jonathan