Preventive Maintenance Model Work Orders Bills Of Materials

Jeff George

Jeff George

Well Known Member
What are the steps for assigning a BOM to a Model Work Order so that it gets used every time the PM comes due? My team has created an Item Master/Branch for a 'maintenance kit' and assigned that Item as the Inventory Item Number for a test piece of equipment. But the Work Order is not including any Parts List. The UBE is set up to include it. I'm sure it's a simple process we're overlooking, but I'm just not sure what it is.
 
Hi,
I'm assuming you are using R12807 to generate WO. The UBE will be using BOM for Maintenance Kit (APL) Item Number/Branch. You should check BOM Type specified on Model Work Order header. Also, there can be an issue if generated WO has empty planned start date - the UBE will be verify BOM effectiveness on that date. In this case, check your PM Rules.
 
The BOM item needs to be assigned to the model work order, not the equipment master.
 