P1207 PM Schedule WO generation

JohnEcc

Active Member
I have daily plant check routines set up as equip items with a P1393 maint rule set up to generate Work Orders when 70% due (i.e will produce planned work orders 2 days before the weekly check is due). The PM schedule status 01 states 'date completed' as the date the planned 03 job was generated. Shouldn't the actual WO closure date then overwrite the ' completed date' in the PM 01. Each week the WO start dates are short by an additional 2 days as the 03 planned jobs are driving off the previous 70% due generation dates. Anyone got any ideas out there?

cheers,
JohnE
 
JDE Repsonse line have indicated they are preparing a SAR on this issue. A variation is that the PM work order closure,R17714, update date is populating the 'date completed' on the P1207 PM Schedule. This is incorrect. The date completed on the P1207 should be the completed date entered on the P48201
 
Response Line have advised SAR 6111473 now at status 37 Ready for ESU build
 