Has anyone had a problem with WO completion labor rates (Run Labor/Run hours) rounding up?
Our system currently rounds to 2 decimal places, versus the desired decimal places of 4.
This is currently giving us a variance.
The problem is when the routing is attached to the work order or schedule there is only two places to the right of the decimal. This will truncate the resolution of the time basis code calculation. In turn leaving a planned variance for each transaction.
Any ideas to resolve this issue?
Thanks!
John
Portland Or.
Our system currently rounds to 2 decimal places, versus the desired decimal places of 4.
This is currently giving us a variance.
The problem is when the routing is attached to the work order or schedule there is only two places to the right of the decimal. This will truncate the resolution of the time basis code calculation. In turn leaving a planned variance for each transaction.
Any ideas to resolve this issue?
Thanks!
John
Portland Or.