Dear List,

We plan to upgrade our NT servers to Windows 2000 in the near future,
however, I have one question. Should the deployment server be completed
first or last. If we do the deployment server first will I still be able to
build server packages to the NT boxes. Any other potential problems

Thanks in advance,

Ian

Xe, sp 16.1, Oracle 8.1.6, NT



Xe, Oracle 8, NT
 
Ian :

I've done it both ways, and all work fine.
As a potential problem, try to keep your Deployment server on MDAC 2.5; some
table conversions
don't run fine on MDAC 2.6; and I also suggest you not to install Terminal
Server Services and
Web Server Services on both Enterprise and Deployment.