Enterprise One Planning Workbench

alanmacc

Member
Hi All

We are using Enterprise One currently but also using an external system excel based for our planning of materials, PDP system, I know that JDE has an MRP module as well as a planners workbench, my question is to anybody who is currently using these modules......... do they work ok with constrained materials? i.e. if 95% of paterials are readily available in 6 weeks but the remaining 5% are not available for 25 weeks, the system will plan to have orders made and materials available in the store closer to the 25 seeks to ensure that you are not over stocked?

I hope this makes sense

Cheers
Alan
 
Hi.

Post this in the Applications Forum and add your system information in the signature (EnterpriseOne Version, Tools Release, etc)
 