Scheduler showing wrong Job status

navin_JDE

Active Member
Hi,
in P91300 we have some jobs schdeuled to run daily. today we found that 2 jobs status in P91300 as Error:Could not submit. but if we check the status in WSJ it is showing ths staus for that job as DONE. the scheduler application is showing wrong status. anybody has ever faced this issue plese help.

Thanks,
Naveen
E1, 8.98,windows.
 
Answers to the below questions would enable the list to make an informed analysis of your issue:

1. Whats your database type?
2. Does it show that status for a particular job or all the jobs?
3. Were there any network drops recorded during the time the job was submitted to the server?
 
Hi,
1. Databse is SQL
2. No out of 8 scheduled jobs it is showing this for 2 jobs for the remaining all status is DONE.
3. No no N/W issues. Actually the Jobs run successfully but the scheduler is showing it as error.

When i checked the log files for the failed jobs there is nothing sucpicious. I attached them.

Thanks in advance
Naveen,
E1,898,Windows, SQL.
 

Attachments

  • 144480-R007031logon 0324 .txt
    1.7 KB · Views: 74
Hi,
Today again 2 UBEs are showing error in Scheduler.These 2 are not the previous day's UBEs. Yesterday's UBEs which run today are completed successfully but 2 other UBEs are showing the Job Status as Error: Could not submit. Actually these 2 UBEs are completed successfully but the scheduler is showing wrong status.

Thanks a lot.
Naveen
E1,898, sql. windows.
 