Calculating routing request date with Leadtime offset

SMF4737

Member
I am using a process item with leadtime offset in the BOM and set up hrs in the process routing. When I review the start date and requested data on the WO they do not match, I can not figure out how the dates are calculated. For example the co-products in step 20 have a start/requested date one day before the work order and there is no leadtime offset or setup time. Some steps are a day earlier and some are a day later than the should be (apparently).
 