Sequence of UBEs in a monothread queue

bub

Member
Hi List,

I need your help about run sequence of UBEs.
I explain my problem :

I've a BSFN (N4200310) who call UBE R42750.
At the end of this BSFN, I've add a call for a custom BSFN who do some updates and finish with a call of R42565.

This 2 UBE are running in the same Queue who's monothread.
Chronologicly, the R42750 is call before the R42565. If you look in WSJ, the Job Number of R42565 is greather than the Job Number of R42750.
But, the R42565 run BEFORE the R42750.

If I mapped this 2 UBE on Local, the UBEs run in the good sequence. But, if the UBE are mapped on server, the sequence is KO : R42565 run BEFORE R42750.

Plat-form : PeopleSoft E8.10 (Unix)

I cannot understand why and how this situation is possible ...???... And you ???

Thanks.

Regards
 
Bub,

Were you able to find out anything on this?

I am currently working with 8.11 SP1 and am finding that the R42750 appears to stay in the queue in a waiting status for up to 3 minutes even though there are no jobs processing through that queue???. I am wondering whether this delay is to allow for Sales Order Processing to complete its asynchronous activities before the Reprice starts? (so that it doesn't start repricing a part-loaded Sales Order) - only a theory though!

Hopefully someone could throw some light on this?

Cheers,
 
Back