cobb87 Member Mar 9, 2022 #1 I am new to JDE, and I am attempting to roll a part number that has been set up with the CM 09. When I freeze the cost, it does not flow through the 'cost ledger'. How do I get the cost to update correctly for an 09 part?
I am new to JDE, and I am attempting to roll a part number that has been set up with the CM 09. When I freeze the cost, it does not flow through the 'cost ledger'. How do I get the cost to update correctly for an 09 part?
Devo Well Known Member Mar 9, 2022 #2 You do not simulate and freeze costs when using actual costs. Costs are determined after MFG Accounting and Variance Accounting are completed