R41052 - Future Cost Update

Report_Writer

Active Member
Future Cost Update UBE has a PO 'Enter 1 to purge future cost records' but not sure what exactly this would do. Can anyone comment?

Thanks
RW
JDE 8.12, 8.97, SQL Server 2005
 
1. Enter the Cost Method you wish to be updated with a future cost. If left blank, the cost to be updated is the one associated with your current Inventory/Sales costing method.

This is the cost method, you would be updating.


4. Enter 1 to purge future cost records....
This relates to the Data selection cost method.

1 is for to.
4 is for from.

If you select '1' in option 4, this would purge the records from the data selection you give.

Suppose if you give data selection
Cost method (F4105) (LEDG)[BC] is equal to 'IC'

and PO is '02'

Then after processing all the records, 02 cost method records will be updated with 'IC' cost and then 'IC' cost records will be purged.

Hope this helps you.

Thanks.

Bala
 
Back