P4210 - pick date tie to Supply and Demand

Djohnson

Djohnson

Well Known Member
In Sales Order Entry detail there is a scheduled pick date for the item/line. In the detail description of this field, PDDJ, it mentions the S&D program (P4021) used thisa date to calculate available to promise info. Thus:

Question #1 - Is there a way to make this date in the order to automatically revert to a day earlier. Say the requested date is August 31, but we want the pick date to be August 30.

OR

Question #2 - Can the S&D program be set to figured this out. I can not seem to find the trigger in the values.

Confusing? Absolutely, especially to our manufacturing people who need to have a visual date to plan ahead. At this moment our sales people and manually changing the pick date on all sales order detail lines.
confused.gif
 
Dan--

Have you looked at the Order Prep Days preference? It seems to me that if
you set that to 1 it should back off the scheduled pick date by 1 day.

Andy Klee
www.JDEtips.com
 
Re: RE: P4210 - pick date tie to Supply and Demand

Hi Andy...
Thanks, not familiar with this where is it found?

Dan
 
Re: RE: P4210 - pick date tie to Supply and Demand

It's with all the other preferences on one of the Sales Order menus.
 