B7.3 Multifacility MRP generation _ Considering onhand in two different branchplants in different company

  • Thread starter ramprasadchoudhury
  • Start date

ramprasadchoudhury

Member
Hi ,

we have three different company in different locations. we need to plan MRP in one plant in one company considering the Quantity onhand in other two companies as well as the onhand available in the plant where the MRP runs. How can we do the setup in JDE ? need your input if anyone worked on this scenario.

Thanks
Ram
 
Under the "Planning" tab and under Branch Relationship Revisions you can add plant relations for supplying items to other units. From here you can include LT's and other data.

Once this data is in and your branches put in any SO/RO or other transaction between the supplier branch, your unit will receive MRP messages for such items.
Hope this helps!
 