MRP Messages Missing from a Branch

richchipper

Well Known Member
We have set up a pass-through branch for company to company ordering. however, when I check supply & demand, I see that there are demand messages but no prompts for supply. I have the branch relationships set up for one branch to order from the other. It's been a while since we set up new branches so I'm not sure if there is an MRP setup that we are missing. Thanks in advance.
 
Do you have your shop floor calendar set-up for the new branch plant? Also, R3483 processing option 2 under Multi-facility should be set to 2.

-M
 
I think your system is working right if my understanding is correct......DRP/MRP should only generate transfer order messages ( like OT) in demand BP
which when processed by the planner generate ST/OT orders.

Thanks
aaro
 
Back