Andre_Jille
Active Member
Hi,
We're on E8.12, using R3482 to suggest Purchase Orders, this functionality uses Calendar days to determine when to place a Purchase Order with a Vendor for Purchased Items (and uses a Workday Calendar for Manufactured Items to initiate Work Orders).
Since our Suppliers are mainly on a regular 5-day week we're exploring the options to use a Workday Calendar for Purchased Items as well, however could not think of easy options for this.
One option is to simply increase lead time, eg. 7 days to 9 days, another option might be utilizing Transportation Module, just to use the Calendar features of this, however not sure if this works with the MRP program or kicks in only at a later stage.
Did anyone come across this requirement before and if yes: how was this tackled?
Thank you.
We're on E8.12, using R3482 to suggest Purchase Orders, this functionality uses Calendar days to determine when to place a Purchase Order with a Vendor for Purchased Items (and uses a Workday Calendar for Manufactured Items to initiate Work Orders).
Since our Suppliers are mainly on a regular 5-day week we're exploring the options to use a Workday Calendar for Purchased Items as well, however could not think of easy options for this.
One option is to simply increase lead time, eg. 7 days to 9 days, another option might be utilizing Transportation Module, just to use the Calendar features of this, however not sure if this works with the MRP program or kicks in only at a later stage.
Did anyone come across this requirement before and if yes: how was this tackled?
Thank you.