  1. B

    E9.1 Demand not showing from one branch to another

    Just in case anyone else ever comes across this problem, I thought I'd post our solution here. I found that the expiration dates in F3403 were set to 12/31/2020 and instead of using branch leadtime or defaulting to a value of 1 or 0 days, it just didn't plan that demand after these entries...
  2. B

    E9.1 Demand not showing from one branch to another

    Hi all, we're seeing an odd situation where planned POs in one branch that are pointed to another branch do not show demand in the supplying branch. It's working properly up to the end of 2020, but we then see no demand coming through to the supplying branch in 2021 and beyond. I know this has...
  3. B

    Question regarding line type W and related work orders

    Thanks for pointing us in the proper direction here Larry. Looks like all my versions for P48013 do have the "Cutoff Status Code" set to a value of 10. I did notice a few that have a value of 05 in the "Changed Status Code (After Cutoff)" processing option though so I'm guessing those are...
  4. B

    Question regarding line type W and related work orders

    We use line type W fairly extensively in our operations, usually for configured items. We occasionally see an issue where after a work order has already been completed the status is reset if any edit is made to the sales order with the related W line type, even just a freight method or ship to...
  5. B

    Work orders not generating routing when created from W line type on sales order E19.1

    Hi all, we're having an odd issue and I was hoping someone here might be able to point me in the direction of more factors to check into. We have a large group of items in one of our branches that if we manually create the work order and generate bills and routings (R31410) we have no issues...
  6. B

    Work Order Backscheduling - date changes and routings

    And sorry, I'm realizing now I should have posted this in the Applications subforum...
  7. B

    Work Order Backscheduling - date changes and routings

    Hi All, last week we made a largely successful transition from OneWorld all the way up to EnterpriseOne 9.1 but I've got a minor issue I haven't been able to discern the cause of or correction for. Currently when we change the request date on a work order header and move the date in to an...
  8. B

    Receipt Routing - Flash Message / Notification ?

    Thanks Terry. It sounds like I need to experiment with the Receipt Travelers. I'm just worried about the waste that having the receipt staff scan through 75 of them daily, to identify the 2 that need to go to inspectiong, creates. Will the Traveler generate only if a receipt routing is attached...
  9. B

    Receipt Routing - Flash Message / Notification ?

    Good Day all, I'm working with OneWorld Xe and have a question regarding use of receipt routings. My company currently does not use receipt routings, but I am researching the possibilty of using these for items we want to do receipt inspection on, and only those items. I've gone through the...
Top