Copy cost from one branch to another Branch for finished good.

amathiou

Member
Hi,

I have a problem with some finished goods copying over to receiving branch plants.some of them have additional cost components X1, X3, X4, etc...when the copy from one branch plant to another is taking place,if they have additional cost components it is rolling up the total cost of the finished from the manufacturing branch into A1 in the receiving branch, it is then also copying all X additional cost components and adding them on again.so I am getting a different price across the 2 branch plants. And it is happening for some codes not for all of them. Any suggestions?

Thank you
 
Back